2026 MGHPCC power downtime June 16-18, 2026

The yearly power downtime at our Holyoke data center, MGHPCC, has been scheduled. 
This year's power downtime will take place on Tuesday June 16, 2025. 

This will require FASRC to begin shutdown of our systems beginning at 9AM on Monday, June 15th.
We have worked to reduce the total outage time this year.
We will begin power-up on Wednesday June 17th with an expected return to full service by 9AM Thursday June 18th.

 

 

      • Monday June 15th -  Power-down begins at 9AM
      • Tuesday June 16th - Power out at MGHPCC
      • Wednesday June 17th - Maintenance tasks and then power-up begins
      • Thursday June 18th - Expected return to full service by 9AM

Maintenance:

  • TBD
  • TBD

Updates will be posted on our status page: https://status.rc.fas.harvard.edu/
Note that you can subscribe to receive updates as they happen. On the status page, click Get Updates.

Notices and reminders will also be sent to all users via our mailing lists.